# 2740. Why could February appropriations still miss an August 1 clothing promise in 1890?

**Finding.** In his 1890 report, the Commissioner of Indian Affairs described a procurement sequence that could begin only after the Indian appropriation act was signed, yet still required advertising, sample review, awards, signed contracts and bonds, manufacturing, and shipment. He said that **even if the bill became law as early as February**, under the most favorable circumstances **goods could not be shipped until the end of June**. For clothing promised under treaties with the Crow, Sioux, Cheyenne, Arapaho, Ute, and other peoples, he described an **August 1** deadline for delivery at the *Government warehouse on the reservation*, and called it “a promise which this office has never been able to keep.” A late-June earliest shipment is not a warehouse delivery by August 1; nor does the report establish a dated delivery history for every named nation and year.

The [Commissioner's printed p. CXXII, PDF leaf 65](https://www.doi.gov/sites/default/files/T-21922.pdf#page=65), attributes the starting constraint to a **Second Comptroller ruling**: no contracts could be executed until the President signed the appropriation act and it became law. He gives **at least three weeks** for advertisements, **two to six weeks** to abstract bids, classify many samples, and make awards, and then **fifteen to twenty-five days** before geographically scattered bidders' contracts could be executed and approved by mail. Blankets, clothing, wagons, boots, shoes, and other items still had to be manufactured after contract and bond approval. These are stages in his account, not evidence that every order took exactly the sum of the quoted intervals or that each item was manufactured for the same length of time.

The Commissioner urged that the bill should **never pass later than mid-February**; he blamed late appropriations for goods arriving only late in winter and the resulting hardship. Printed p. **CXXIII** (the other printed page on [the same PDF leaf](https://www.doi.gov/sites/default/files/T-21922.pdf#page=65)) continues the sentence: the favorable February scenario allowed shipment **only by the end of June**, whereas the treaty promise he describes was **warehouse delivery no later than August 1**. Shipment, warehouse delivery, and ultimate issue to a person are three different events. The neighboring report's [80,407-package fiscal-year shipment tally](https://www.doi.gov/sites/default/files/T-21922.pdf#page=64) does not supply the order-by-order shipping or receipt dates needed to test the August deadline.

**Limits.** The printed account is the Commissioner's explanation and statement about the Office's performance, not the text of the Comptroller's ruling or a treaty-by-treaty legal analysis. “Never been able to keep” is his broad characterization; it does not prove that every clothing allotment for every named people in every year was late, or identify any individual consignee's receipt. The statutes and dated contract, manufacturing, bill-of-lading, warehouse, and issue records would be needed to reconstruct any particular appropriation-to-delivery path. Nothing here establishes that a specific contractor breached a deadline or that Congressional timing was the sole cause of a particular late delivery.

**Source:** Commissioner of Indian Affairs, *Annual Report* (1890), [printed pp. CXXII–CXXIII, PDF leaf 65](https://www.doi.gov/sites/default/files/T-21922.pdf#page=65), procurement-calendar and clothing-delivery paragraphs, checked against the page image.