# 2702. Fort Smith and El Paso: fifty miles of route maps approved, no construction shown in the office file

**Question.** Did the Fort Smith and El Paso Railway's 1888 congressional right-of-way grant and its approved maps establish that it had begun building through Indian Territory by 1890?

**Finding.** No. The Commissioner of Indian Affairs said in the **1889** report that the Fort Smith and El Paso Railway, along with two other grantees, **“appear to have taken [no] steps to avail themselves”** of their respective rights; the cited Fort Smith act was **25 Stat. 162**. In the **1890** report, the office described a real subsequent change in the *mapping* record: maps of the definite location of the **first and second 25-mile sections** of the Fort Smith and El Paso line had been **approved November 14, 1889**, while maps of the **third and fractional fourth sections** were **awaiting approval**. The same paragraph then draws the crucial boundary: **“There is nothing on file in this office to show that the company has begun the work of construction.”** This sentence straddles printed pages LXIX–LXX; the “25 miles each” at the foot of LXIX continues into the November approval and construction-file statement on LXX. Thus the 1889 statement was an administrative impression at that date, not an assertion that the company would never file a map; conversely, the 1890 approvals were not evidence of grading, laid rails, or operation.

Congress had authorized an Arkansas corporation by the **May 30, 1888 act, ch. 337, 25 Stat. 162–165**, to locate a line from near Fort Smith through **Savanna in the Choctaw Nation**, near **Cherokee Town in the Chickasaw Nation**, and toward the southwestern corner of Indian Territory. Sections **1 and 6** required a definite location submitted to and approved by the Secretary of the Interior in **25-mile working sections before construction of each section**; §6 also required route maps filed with the Secretary and the principal chiefs, and grading within six months after filing a located portion or **that location** would be void. Section **3** required compensation for property and damage to individual occupants before construction through their land, subject to its referee, court-appeal, and deposit procedures. Section **5** prescribed **$50 per constructed mile**, payable in **$1,250 installments as each 25-mile working section was graded**, plus **$15 per constructed mile annually** while the Territory remained Indian-owned and occupied, with an option for a tribal council to dissent from the statutory allowance and pursue determination by referees. These are separate conditions and payments: approval of a line is neither proof of grading nor proof of compensation.

Section **9** called for at least four such sections, or **100 miles**, built within **three years after passage** and the remainder within five years, with forfeiture **as to the portion not built** under its terms. The 1890 report preceded the first three-year anniversary in May 1891. Nor does the November 14 approval date tell us when maps were originally *filed* for purposes of §6's six-month grading rule. A void location, actual forfeiture, a violation of occupant-payment conditions, or a final failure to build **cannot be inferred** from the office's lack of a construction document in this passage.

There is an additional mapping detail, not a contradiction. In its account of the *Choctaw Coal and Railway Company*, the 1890 Commissioner said that Fort Smith and El Paso **also filed a definite-location map through “The Narrows”** in the Choctaw Nation, and that the Department approved both competing maps under conditions allowing both lines to be constructed through the passage. That paragraph does not identify the Fort Smith map as its third or fractional fourth section or date the conditions. It cannot erase the separate statement that the third and fractional fourth section maps were awaiting approval. The Narrows dispute and the Choctaw Coal company's later enclosure complaint concern another grantee and are treated separately in [finding 2685](2685-choctaw-coal-railway-narrows-corridor-complaint-1890.md).

**Why this matters.** A congressional franchise, a located corridor, an approved working-section map, a graded roadbed, an operating railway, and a compensated occupant are different documentary states. Here the Indian Office explicitly reported the first two section-map approvals while explicitly declining to say its files showed construction. To turn either sentence into a claim of a built Fort Smith–El Paso route—or a claim that nothing was ever built—would invert the source's limits.

**Primary sources.**

1. Commissioner of Indian Affairs, *Annual Report* (1889), printed p. 38, [PDF leaf 48](https://archive.org/download/annualreportofco188900unitrich/annualreportofco188900unitrich.pdf#page=48), “Indian Territory” paragraph naming the Fort Smith and El Paso, Kansas City and Pacific, and Paris, Choctaw and Little Rock companies.
2. Commissioner of Indian Affairs, *Annual Report* (1890), printed pp. LXIX–LXX, [PDF leaf 38](https://www.doi.gov/sites/default/files/T-21922.pdf#page=38) and [PDF leaf 39](https://www.doi.gov/sites/default/files/T-21922.pdf#page=39), first/second section approval, third/fractional fourth pending, no construction shown in office files; also the separate Narrows map paragraph on LXIX.
3. Act of May 30, 1888, ch. 337, [25 Stat. 162–165](https://www.govinfo.gov/content/pkg/STATUTE-25/pdf/STATUTE-25-Pg162.pdf), especially §§1, 3, 5–6, 9.

**Evidence limit.** The approved maps, submission and filing dates, construction contracts and inspection records, chiefs' filed copies, grading surveys, occupant awards and receipts, and later project fate have not been established here. “Nothing on file in this office” describes a reported file state, not a comprehensive proof of never having constructed a railway. The identity and chronology of the separate Narrows map relative to the pending third/fractional fourth sections remain open.