# 2685. The Narrows maps were conditionally approved; a Choctaw railway enclosure complaint remained for another report

**Question.** Did the 1890 Commissioner's account establish that the Choctaw Coal and Railway Company had unlawfully fenced more land than its right-of-way grant allowed?

**Finding.** The Commissioner of Indian Affairs reported several different acts of administration, **not a completed judgment on the enclosure**. A definite-location map for the railway's **tenth section, 26 miles**, was submitted to the Department on **November 12, 1889**. It passed through a gap called **“The Narrows”** in the Choctaw Nation, where the **Fort Smith and El Paso Railway** also filed a map. The Department **approved the two maps under conditions allowing both roads to be constructed through the passage**. A separate **fourteenth-section map** was approved **December 31, 1889**, and **seven station-ground plats were submitted** April 12, 1890. Submission of those plats is not stated to be their approval.

The company **tendered a $1,000 draft on April 3, 1890** for right of way on a part of its line **which the company said it had graded**. The Commissioner then says complaints had been filed alleging that the company **enclosed a strip of greater width and area than the grant authorized**; the complaints **“will be made the subject of a separate report.”** The available paragraph does not give the survey of the enclosed strip, the complainants' evidence, the company's response, a referee award, or the promised report's conclusions. It does not prove that the full $1,000 was accepted, credited, or distributed. Dividing $1,000 by the statute's $50-per-mile allowance yields a mathematical **20 miles**, but the passage does not state that this was the surveyed or approved length, or specify the draft's accounting.

The enabling **February 18, 1888 act, 25 Stat. 35–39**, sets a **100-foot-wide right of way** for the main line and branch under §2. It separately permits a station strip **200 feet wide and 3,000 feet long** in addition to the corridor for every ten miles, and additional land at heavy cuts or fills **not exceeding 100 feet on each side of the right of way, or the portion actually in the cut or fill**. Those express exceptions mean a photographed or reported enclosure wider than 100 feet, without its station or engineering context, would not by itself establish an excess under the act. Land taken under the grant could not be leased or sold by the company and was limited to necessary railway purposes; unused portions would revert under the statutory terms. Sections 3 and 5 distinguish individual occupant damages from a tribal **$50-per-mile** benefit and an additional **$15-per-mile annual payment** while the Territory was Indian-owned and occupied. Section 6 requires filing route maps and Secretarial approval in **25-mile sections before construction of each section**. The **February 13, 1889 amendment, 25 Stat. 668–669**, rewrote §1's route description; it did not replace the §2 width and station rules.

**Why this matters.** The Narrows decision addressed competing routes through a choke point; it was neither blanket approval of every station plat nor adjudication of an alleged excessive enclosure elsewhere. The company-reported grading, tender, and complaint each have different evidentiary status. Calling the complaint proved theft would go beyond the record, while calling it resolved because two maps were approved would also erase an open question.

**Primary sources.**

1. Commissioner of Indian Affairs, *Annual Report* (1890), printed p. LXIX, [PDF leaf 38](https://www.doi.gov/sites/default/files/T-21922.pdf#page=38), Choctaw Coal and Railway paragraph (maps, conditional Narrows approval, April draft, complaint and promised separate report).
2. Act of February 18, 1888, ch. 13, [**25 Stat. 35–39**](https://www.govinfo.gov/content/pkg/STATUTE-25/pdf/STATUTE-25-Pg35.pdf), especially §§2–3, 5–6 (corridor and exceptions, damages, tribal compensation, map approval).
3. Act of February 13, 1889, ch. 152, [**25 Stat. 668–669**](https://www.govinfo.gov/content/pkg/STATUTE-25/pdf/STATUTE-25-Pg668.pdf) (amended route in §1, not the width provision).

**Evidence limit.** The approved conditional maps and actual conditions, station-plat decisions, grading and fencing surveys, deposit and disbursement records, complainants' exhibits, company answer, and separate report were not located. The allegations remain allegations, and the statutory width cannot be applied to an unsurveyed strip without checking its station and cut-or-fill exceptions.